Fund Utilization under Constituency Development Programme in Kukatpally Constituency

Fund Utilization under Constitunecy Development Programme in Kukatpally Constituency
GHMC HMWSSV
Year No.Of Works Sanctioned Disbursed Status No.of Works Sanctioned Disbursed Status
2010-11 5 49.51 100% Completed 13 50.1 100% Completed
2011-12 7 74.21 100% Completed 31* 72.31 100% Completed
2012-13 5 49.51 25% Completed

3 community halls pending due to site disputes

13 49.75 100% Completed
2013-14 5 47.75 Roads, Culvert Drains and Community Halls To be started 23* 116.7 60% 50% Completed, 50% is in various stages of implementation
2013-14 12 38 Administrative Sanction Received
Total (Lacs) 220.98 326.86 547.84
Note: * 50% matching grants from HMWSSB
Rs.3.45 cr works completed. Balance is work in progress
Friday, March 28, 2014 - 18:48